NCC Begins Bangalore Metro Airport Line’s Test Piling Work

[ad_1]


NCC Ltd. over the past fortnight has started test piling activity across all 3 packages of Bangalore Metro’s 37 km Airport Line (Blue Line) which will link Bengaluru’s Kempegowda International Airport (KIA) to KR Puram.

These 3 elevated sections of Bangalore Metro Phase 2B project range from 11 to 15 kms and consist of 15 out of the 17 stations planned on the line. NCC was awarded 3 LOA contracts in November 2021 with completion deadlines ranging from 24 – 27 months.

Route of Bangalore Metro’s Airport Line with key stations marked – view Bangalore Metro Phase 2 info & route map with all stations

This post focuses on the 11.678 km Package-2 which will connect Hebbal – Bagalur Cross (chainage 10072m to 21500m) with a 250m pocket track and 5 elevated stations at Hebbal, Kodigehalli, Jakkur Cross, Yelahanka and Bagalur Cross.

NCC’s team here has completed concreting 4 out of 10 test piles each with a 1m diameter. These 4 range between 24-30m deep, and are located near BSF’s Campus in Yelahanka (Pier AP709 to AP710) and Bagalur Cross Underpass (Pier AP668 to AP 669). This includes 2 vertical load test piles and 2 lateral load test piles.

Ready to bore!
Pile cage getting inserted

Actual piling for the line’s construction is planned to start within a week! When that happens, I’ll update all key figures across the Bangalore Metro Phase 2B and Quick Snapshot pages to reflect the change.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.