Metros Tenders

ST Only Bidder for Chennai Metro Line 3 & 5’s Platform Screen Door Retender

[ad_1]


Singapore’s ST Engineering Electronics Ltd. is once again the only bidder for Chennai Metro Line 3 & 5’s Platform Screen Door contract (Package ASA12A) after Chennai Metro Rail Ltd (CMRL) opened technical bids on Tuesday.

Both these under construction lines of 116.1 km Chennai Metro Phase 2 project will run in a north-south orientation to connect Madhavaram – SIPCOT (45.4 km Line-3) and Madhavaram – Sholinganallur (44.6 km Line-5) with a mix of elevated & underground stations.

Platform screen doors (PSDs) with half-height will be installed at all elevated stations for enhancing passenger safety with primary goals to prevent suicides & accidents during passenger movement.

The scope of this contract includes Line-3’s 10 elevated stations between Sholinganallur Lake – SIPCOT 2, awarded to RVNL in January 2023, and Line-5’s 29 elevated stations between Grain Market – Elcot which are under construction by HCC – KEC JV and Larsen & Toubro.

CMRL had originally invited tenders for this contract in October 2022 with an unknown estimate and 1965 day deadline. Technical bids were opened in February 2023 to reveal ST as the only bidder and the tender was cancelled in May 2023. Bids were re-invited in June with a 800 day deadline.

Brief Scope: Design, Manufacture, Supply, Installation, Testing and Commissioning of Platform Screen Doors for Corridor 3 (Sholinganallur Lake to Sipcot 2) and Corridor 5 (Grain Market to Elcot) of CMRL Phase II.

CMRL’s May 2023 updated Chennai Metro Phase 2 Map – view Phase 2 information & route map
Representational only: Half-height platform screen doors at Mumbai Metro’s new Red Line – Photo via Darshil Parmar

CMRL wasn’t satisfied with just ST’s participation in the original tender’s round, so they’ll now have to make a call in the interest of time – whether to (1) cancel the tender and hope for better participation in the next round, or (2) go ahead and evaluate ST’s technical bid and open their financial bid if all ducks are in a row on the technical side.

CMRL has another tender (Package ASA09) for PSDs on Line-3’s Nehru Nagar – Sholinganallur section and Line-5’s Assissi Nagar – Koyambedu section. Bids are currently scheduled to open on October 11, so stay tuned.

A list of all Chennai Metro Phase 2 civil & system packages and their status can be viewed here.

For more updates, check out the Chennai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG



[ad_2]

Source link