Bangalore Metro’s Whitefield Line’s Signaling and Electrification Ready
[ad_1]
Alstom Transport India has announced the completion of signalling & electrification works for Bangalore Metro’s 15.257 km Reach 1A & Reach 1B (Baiyyappanahalli – Whitefield) extension of the Purple Line.
This development now allows Bengaluru Metro Rail Corporation Limited (BMRCL) to begin full-fledged dynamic train testing on this extension which I expect will open in mid-2023.
This milestone’s scope of course excludes the roughly 2.25 km Byappanhalli – Benniganahalli (Tin Factory) – KR Puram section where civil construction work is still underway – see details at the bottom.
Bangalore Metro’s Whitefield extension is the longest extension of Phase 1 lines in the 73.92 km Bangalore Metro Phase 2 project. In September 2022, Texmaco Rail and Engineering in September had completed casting all 24 track turnouts for it.
![](https://themetrorailguy.com/wp-content/uploads/2020/11/BangaloreReach1BRouteMap.png)
Back in October, BMRCL had started basic trial runs from Whitefield metro station to Pattandur Agrahara metro station – a distance of 3.5 kms. Since then, they’ve slowly been extending testing to the line’s western portions with a primary goal to check for Schedule of Dimension (SoD) clearances.
![](https://themetrorailguy.com/wp-content/uploads/2022/12/AlstomBangaloreMetroTrial.jpg)
The line’s 2.25 km Byappanhalli – Benniganahalli (Tin Factory) – KR Puram has gone through several design changes and affected by land acquisition hurdles.
ITD Cementation India today (Friday) was going to complete launching a 65m Open Web Girder (OWG) over the Indian Railways’ lines at Benniganahalli, but that has postponed.
Per a BMRCL official who spoke with Christin Mathew Philip at TOI, “This is due to the delay in installation of large no. of HSFG bolts & tightening them to design torque. Hence, the launching of OWG is postponed by few days“.
A cool drone view of the OWG posted by BMRCL can be viewed here.
As far as Whitefield metro line’s opening goes, I’m still looking at a mid-2023 opening. BMRCL has so far transported only one train-set, by road, to the under construction Kadugodi Depot where progress stands at 72.64% according to BMRCL’s December 2022 newsletter.
The depot has major civil and systems installation work pending which makes me believe BMRCL will start operations between KR Puram – Whitefield only after end-to-end civil and track-work on the entire extension is completed. This will allow them to feed trains trains from Byappanhalli Depot.
![](https://live.staticflickr.com/65535/52580233566_78772147da_o.jpg)
For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.
– TMRG