Bangalore Metro’s TBM Urja Records Breakthrough at Pottery Town

SHARING HELPS OTHERS



Larsen & Toubro’s Tunnel Boring Machine Urja (DZ670) on Thursday afternoon recorded its second breakthrough at Pottery Town Station for Bangalore Metro’s 21.386 km Pink Line (Reach 6).

This Ø6.67m CRCHI slurry machine is part of the Bangalore Metro Phase 2 project’s 2.884 km package RT-03 (Shivajinagar – Tannery Road) which was awarded by the Bangalore Metro Rail Corporation Ltd (BMRCL) in February 2019.

Photo via Srivas Rajagopalan

After completing the 862m Cantonment – Shivajinagar north-bound tunnel in September 2021, it was then recommissioned in December 2021 to build the 906.702m Cantonment – Pottery Town Station section’s north-bound tunnel.

Route of RT03 – view Bangalore Metro Phase 2 info & route map

L&T’s official tunneling estimate for this drive was 280 days and they completed tunneling within just 190 days.

Bangalore Metro’s TBM Urja Records Breakthrough at Pottery Town
Photo via Keshav Gupta

A video can be viewed here.

The machine will now be dragged through the station box and commissioned on its third and final 710.64m assignment towards Shadi Mahal TBM Retrieval Shaft, located south of Tannery Road Station.

Per BMRCL’s June newsletter, Urja’s sister machine – TBM Vindhya (DZ671) working on the same stretch has completed 390.6m for the south-bound tunnel, and I reckon it should arrive at Pottery Town in Q4 this year.

With this development, approximately 47.4% of tunneling work for Phase 2 (total scope: 20,855m) has been completed with 9 out of 26 breakthroughs recorded: 3 on Package RT-01 by Afcons, 2 on RT-02 by L&T, 3 on RT-03 by L&T, and 1 on RT-04 by ITD Cementation.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG