SNC Casts Bangalore Metro ORR Line’s 1st U-Girder

[ad_1]


Shankaranarayana Constructions (SNC) on Friday started pouring concrete to cast the first set of 27.90m U-girders for Bangalore Metro’s 56 km Blue Line on the Outer Ring Road (ORR).

The city’s new Blue Line by BMRCL is being developed in Phase 2A (ORR Line) and Phase 2B (Airport Line) to connect Silkboard – KR Puram – Bengaluru International Airport through 30 stations.

SNC’s casting yard for the ORR Line’s 8.377 km Package 2 (Kodibeesanahalli – KR Puram) is located in Kacharakanahalli near Whitefield (view on google maps). It currently consists of a 146m long casting bed from where 5 U-girders weighing 165 tons each will be cast. Work is underway to add another U-girder casting bed and casting formwork for I-girders.

SNC was awarded ORR Line Package 2’s Rs. 623.55 crore contract in May 2021 with a tight 27 month deadline.

Their scope includes constructing the line’s Kodibeesanahalli – KR Puram section’s 8.377 km viaduct, 7 elevated stations at Kodibeesanahalli, Marathahalli, ISRO, Doddanekundi, DRDO sports complex, Saraswathi Nagar and K R Puram, a 1.097 km depot-line linking to the existing Baiyapanahalli Depot and a 0.30 km pocket track.

Route Map of Phase 2A’s ORR Line-5 (Blue Line) – view Bangalore Metro Phase 2A info & map

Additional snaps can be viewed here and here. Back in January-end, SNC cast Package 2’s first pier (ORP-473) in Doddanekundi – see snaps & details here.

Per BMRCL’s LOA, SNC was supposed to start casting U-girders within 126 days from the award of contract in May 2021, so SNC is running way behind the prescribed schedule. This milestone (Key Date#2) of the contract comes with a penalty of 0.001% of total contract price per day of delay.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG