Bangalore Metro’s TBM Varada Restarts Tunneling to Langford Town

SHARING HELPS OTHERS



Tunnel Boring Machine S-1264 operated by Afcons Infrastructure on Thursday was recommissioned at Rashtriya Military School Station for building the down-line tunnel of Bangalore Metro’s 21.386 km Pink Line (Nagawara – Kalena Agrahara).

Nicknamed Varada, this is TBM S-1264’s second and final drive for the 3.655 km Package RT-01 (Rashtriya Military School Station – Dairy Circle Ramp) of the 73.92 km Bangalore Metro Phase 2 project.

This refurbished Herrenknecht earth pressure balance (EPB) machine was originally commissioned in March 2021 from Rashtriya Military School Station (near Vellara Junction) to build the 596 m up-line tunnel towards Langford Town where it recorded a breakthrough in November 2021. The machine’s parts were then brought back to RMS Station to build the parallel down-line tunnel.

RT-01: Dairy Circle Ramp – National Military School- view Bangalore Metro Phase 2 Info & Map

Per the tunneling plan, Afcons hopes to complete tunneling on this section in 235 days.

Segment for 1st ring being erected

Last week TBM Vamika arrived in the middle of Dairy Circle Station after recording a hidden breakthrough at the station box’s southern-end earlier in the month. Here’s a snap of Vamika (S-1260) and TBM Rudra (S-1259) which is undergoing minor refurbishment at the moment.

In the coming months, both will be recommissioned one after the other towards Lakkasandra Station to build 747.338 meter tunnels which Afcons hopes to complete within 243 days.

For more updates, check out the Bangalore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG





Source link