Alstom Begins OHE Work inside Mumbai & Pune Metros’ Tunnels

SHARING HELPS OTHERS



Alstom Transport India has in the past fortnight began installing anchor bolts to support the 25 kV overhead electrification (OHE) system of Mumbai Metro’s 33.5 km Line-3 (Aqua Line) and Pune Metro’s 16.589 km Line-1 (Purple Line).

Alstom was awarded Mumbai Metro Line-3’s traction contract (Package 11A) by MMRC in February 2018 with a contract value of Rs. 272.43 crore. The exact location for the 1st anchor bolt remains unknown, but I imagine it’s somewhere on the 4.157 km UGC-07’s tunnels between Sariput Ramp and CSIA Terminal 2 Station – the first package where tunneling was completed.

Collage via Vlad Mitroi (Project Director at Egis, part of Mumbai Metro’s MAPLE GC team)

In Pune, MahaMetro awarded Alstom with the 31.254 km Phase 1’s traction contract in January 2019 with a combined value of Rs. 93.40 crore and EUR 4 million.

Work to install Pune’s 25 kV Flexible Overhead Catenary System (FOCS) got underway right away and that enabled MahaMetro to launch trial runs in January 2020 on a 2.4 km elevated section of Line-1 between PCMC to Sant Tukaram Nagar. Since then trial runs have been extended southward to Phugewadi.

Alstom’s team has now started installing the 25 kV Rigid Overhead Catenary System (ROCS) inside the completed portions of Line-1’s 5.019 km twin tunnels between Range Hills Ramp and Budhwar Peth.

Here’s what Pradeep Takale – MD of Systems & Infrastructure at Alstom India had to say:

With immense pride, today I am sharing the photos of the work our teams started in the tunnels of Pune and Mumbai for Rigid Catenary work since last few days with all COVID and EHS protocols and following Alstom’s Zero Deviation policy in a letter and spirit. These are just some of the photos of our frontline warriors who continue to work at site and try to deliver the infratstructure projects critically required for our country.

Collage via Pradeep Takale

95% of Mumbai Metro Line-3’s tunneling has been completed (a TBM breakthrough was recorded yesterday at CSMT) and installation of various systems is well underway, but there’s still no headway on where the line’s depot (car shed) will ultimately be built to house its Alstom train-sets.

For more updates, check out my Home Page!

– TMRG





Source link


SHARING HELPS OTHERS