Metros Tenders

4 Bidders for Mumbai Metro Line 7A & 9’s Electrification Contract CA-176

[ad_1]


Four firms have submitted bids for the 25 kV AC OHE electrification contract of Mumbai Metro’s Red Line (Line-7A & Line-9) after Mumbai Metropolitan Region Development Authority (MMRDA) opened technical bids today.

Both these extensions of the operational 16.5 km Line-7 are under construction by J Kumar Infraprojects via civil Package CA-48 since March 2020.

Underground Line-7A (Gundavali – Airport Colony – CSIA) is a 3.17 km southern extension of Line-7 where the electrification contractor will mostly install rigid OHE (ROCS). Elevated Line-9 (Mira Bhayandar – Dahisar East) is a 11.38 km northern extension of Line-7 and will be equipped with flexible OHE (FOCS).

MMRDA had invited bids for this contract (Package CA-176) in June 2023 with a Rs. 108.01 crore estimate and 30 month deadline.

Bidders

Note: List below shows lead bidders. Some of the bidders may be in a joint venture with others as Siemens has traditionally bid with RVNL, while Leena has bid with Cimechel Electric Company.

  • BNC Power Projects Ltd.
  • Leena Powertech Engineers Pvt. Ltd
  • Siemens Ltd
  • Texmaco Rail and Engineering Ltd.

Scope: Design, manufacture, supply, inst., T and C of 33 kV and 25kV cabling work, complete 25kV OHE system along with switching station, 33kV aux. power dist. system including 33/0.415 kV ASS and complete SCADA sys. for Metro line 9 and 7A of MMRDA, Mumbai

Indicative Route Map of Mumbai Metro’s Line-7A – view Mumbai Metro map & information

The bids have now been sent for technical evaluation which can take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor.

Fun fact: the OHE electrification system for Line-7 (Dahisar East – Gundavali) was installed Leena Powertech Engineers Pvt. Ltd – Cimechel Electric Company JV.

Tunneling works are currently underway for Line-7A by TBMs Disha & Dhruv, while superstructure works are underway for Line-9’s viaduct. A recent video of its physical progress through Mira Bhayandar can be viewed here on YouTube. There’s a long, long way to go.

Back in September 2023, Rahee Infratech was declared as the lowest bidder for Line-9’s track-work (Package CA-167), and MMRDA is currently evaluating technical bids for four of its stations’ architectural finishing work (Package CA-204). With that said, I do not see either lines 7A or 9 opening up before mid-2026.

For more updates, check out the Mumbai section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG



[ad_2]

Source link