Rahee Awarded Surat Metro Line-2’s Track Work Contract

SHARING HELPS OTHERS



Rahee Infratech earlier this month was awarded a Rs. 136.66 crore contract to supply and install standard gauge rails on Surat Metro’s 19.26 km Line-2 connecting Bhesan – Saroli.

This corridor of the 40.35 km Surat Metro Phase 1 with 18 elevated stations is under construction through 2 civil packages: 10.56 km CS5 (Bhesan – Majura Gate) and 8.7 km CS6 (Majura Gate – Saroli).

Gujarat Metro Rail Corporation (GMRC) had invited tenders (bids) for this systems contract in May 2022 financed by Agence Française de Développement (AFD) with an unknown estimate.

Technical bids were opened in September 2022 to reveal 6 bidders and financial bids in January 2023.

Financial Bid Values

Firm Bid (Rs. Crore)
Rahee Infratech 133.66
Larsen & Toubro 139.78
Texmaco Rail and Engineering 141.74
KEC International 143.93
Rail Vikas Nigam Ltd. 148.03
Apurvakriti Infrastructure 151.94

Scope: Design, Supply, Installation, Testing and Commissioning of Ballastless Track from Bhesan to Saroli in Elevated Section Including Connecting Lines to Depot along with Ballasted / Ballastless / Embedded Standard Gauge Track For Corridor-II, Surat Metro Rail Project, Phase 1

Back in January, GMRC had awarded RVNL – ISC JV a Rs. 166 crore track-work contract for 22.77 km Line-1 (Sarthana – Dream City).

A list of all Surat Metro Phase 1 packages and their status/contractors can be viewed here.