Agra Metro Priority Corridor’s Final U-Girder Launched by Sam India

[ad_1]


Sam India Builtwell on Monday launched final of 196 U-girders for Agra Metro Phase 1 project’s 6 km Priority Corridor connecting Jama Masjid Station – Taj East Gate Station.

This major construction milestone on 14.25 km Line-1 was recorded at the depot-line that juts off south of Taj Mahal Station towards PAC Depot where Uttar Pradesh Metro Rail Corporation (UPMRC) received their 1st Alstom 3-coach Metropolis train-set last week.

Photo by Shaad Sy

The 27.90m long curved U-girder weighs approximately 160 MT.

Sam India Builtwell is responsible for the 6 km Priority Corridor’s 3 km elevated section (Package AGCC-01) between Taj Mahal Ramp – Taj East Gate on Fatehabad Road.

UPMRC had awarded Sam India with its Rs. 272.95 crore contract in October 2020 which includes building the line’s elevated viaduct with 3 stations at Fatehabad Road, Basai and Taj East Gate.

Sam India started pier work in February 2021, launched the first pier cap in August 2021, and launched the first 28m U-girder in November 2021.

First section: Taj East Gate to Ramp with the indicative location of enroute stations – view Agra Metro Phase 1 info & route map
Photo by Shaad Sy
Photo by Shaad Sy

Afcons Infrastructure – SAM India Consortium in February started tunneling works on the priority corridor’s 3 km underground section between Jama Masjid – Taj Mahal. So given the quantum of work (civil & system) pending, I reckon we might see commercial operations first start on the elevated section. Stay tuned…

For more updates, check out the Agra section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG