Dilip Buildcon Ltd. (DBL) and Megha Engineering and Infrastructures Ltd. (MEIL) on Monday were declared as the lowest bidder for 3 civil construction contracts of 518 km Bengaluru – Vijayawada Expressway project.

While DBL won Package 7 (their 3rd win), MEIL scooped up packages 8 and 10 (their 6th & 7th wins) in Andhra Pradesh.

This 6 lane access-controlled expressway (NH-544G) will be built under Bharatmala Pariyojana (BMP) Phase 2 with a mix of brownfield-upgrade (36%) and greenfield (64%) routes. Its alignment will pass by Kadapa lending it the name of BKV Expressway.

India’s National Highways Authority of India (NHAI) had invited tenders for their construction under Hybrid Annuity Mode (HAM) in January 2023 with a 730 day (2 year) deadline. Technical bids were opened earlier this month to reveal 9 bidders for packages 7-10.

Package 7 (16 km)

Scope: Audireddipalle (Ch160.000) to Mallapalle (Ch. 176.000)

Estimated Cost: Rs. 740.30 crore

Firm Bid (Rs. Crore)
Dilip Buildcon Ltd. 737.20
G R Infraprojects Ltd. 798.87
Megha Engineering and Infrastructures Ltd. 826.91
Dineshchandra R Agrawal Infracon Pvt. Ltd. 880.00

Package 8 (20 km)

Scope: Mallapalle (Ch176.000) to Kavulakuntla (Ch196.000)

Estimated Cost: Rs. 646.20 crore

Firm Bid (Rs. Crore)
Megha Engineering and Infrastructures Ltd. 622.93
RR Constructions and Infrastructure India Pvt. Ltd. 663.64
Dineshchandra R Agrawal Infracon Pvt. Ltd. 690.00
G R Infraprojects Ltd. 734.77
Dilip Buildcon Ltd. 737.20

Package 10 (24.5 km)

Scope: Narayanmpet (Ch203.500) to Chandrasekharpuram (Ch228.000)

Estimated Cost: Rs. 574.41 crore

Firm Bid (Rs. Crore)
Megha Engineering and Infrastructures Ltd. 564.07 
RR Constructions and Infrastructure India Pvt. Ltd. 603.13
G R Infraprojects Ltd. 644.57
Dineshchandra R Agrawal Infracon Pvt. Ltd. 648.00
Dilip Buildcon Ltd. 694.17
Map via NHAI – view project information and tender list

DBL & MEIL’s bids were lower than NHAI’s estimates in each case, so contracts should be awarded in the coming weeks without a lengthy financial bid evaluation period.

The project’s 343 km greenfield section connecting Kodikonda, AP to Addanki, AP has been divided up into 14 civil packages.

With this development, financial bids have been opened for 13 packages to reveal their most likely contractor, while technical bid evaluation is underway for just 1 package i.e. Package 9 – see a complete tender list and their contractors/status here.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG





Source link


SHARING HELPS OTHERS