L&T, ITD & Afcons Bid for Kolkata Metro Line-3’s Underground Work

SHARING HELPS OTHERS



3 firms – Larsen & Toubro, ITD Cementation India and Afcons Infrastructure on Tuesday submitted bids for Kolkata Metro Purple Line’s 5.05 km UG1 underground contract between Mominpur – Esplanade.

This northern and final section of 15.215 km Line-3 (Joka – Esplanade) will consist of twin tunnels running through 4 underground stations at Kidderpore, Victoria, Park Street and Esplanade. The assigned contractor will be required to deploy two new tunnel boring machines (TBMs) with one TBM on stand-by.

Rail Vikas Nigam Ltd. (RVNL) had invited bids for this contract in July 2022 with an estimate of Rs. 2571.28 crore and an unknown deadline.

IFB No: RVNL_Kol2_MTC_JOKA_UG1

Brief Scope: Design and construction of the ramp and underground metro railway works from mominpur (excl.) to esplanade, 5.05 km (from chainage 9063.00m to 14113.00m) including four underground stations (viz. khidderpore, victoria, park street and esplanade), tunnels by tunnel boring machine and cut & cover method, architectural finishing works, track works, etc. in connection with joka-esplanade metro corridor in the city of state of west bengal, india

L&T, ITD & Afcons Bid for Kolkata Metro Line-3’s Underground Work
Indicative alignment and location of stations on Kolkata Metro’s Line-3 – view Kolkata Metro info & route map

All 3 bids have now been sent for technical evaluation which should take a couple months to complete. When that is done, the financial bids of the technically qualified bidders will be opened to reveal who’s the lowest bidder and most likely contractor for this package.

Back in March 2021, Yuksel Proje – Tumas JV had won this section’s General Consultant (GC) contract. Its twin tunnels will pass through the Military’s Maidan area, near Fort William, and an agreement on its alignment with Ministry of Defence (MoD) has taken a good 10 years to materialize.

I expect a contractor to get assigned in the 2nd half of 2023 with tunneling work starting in mid-2025. Due to tendering delays, I see this section opening up for operations no sooner than 2028, which’ll make the recently operational 6.49 km Joka – Taratala elevated section to function as a stand-alone line, disconnected from the rest of the Kolkata Metro network, for a criminally long time.

For more updates, check out the Kolkata section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG





Source link


SHARING HELPS OTHERS