Gulermak Lowers Surat Metro’s Tunnel Boring Machines at Kapodra

[ad_1]


Gulermak – Sam India Builtwell JV earlier this month began lowering parts of tunnel boring machines (TBM) S94 and S78 at Kapodra Shaft to build Surat Metro’s Phase 1 project.

Both Ø6.61m earth pressure balance (EPB) machines by Terratec are being deployed for constructing tunnels on the 21.61 km Line-1’s 7.02 km underground section connecting Chowk Bazar and Kapodra Ramp.

TBM S94 is an entirely new machine and passed factory acceptance tests (FAT) in China in January. TBM S78 is a refurbished machine and previously saw action in Pune Metro’s Phase 1 project.

Both machines will build a total of 6 tunnels for the 3.46 km Package CS2 / UG1 which was awarded in March 2021 by Gujarat Metro Rail Corporation (GMRC). Gulermak-Sam’s scope also includes the construction of 3 stations at Kapodra, Labheshwar Chowk and Central Warehouse.

Route of Surat Metro’s underground section from Chowk Bazar – Surat Railway Station – Kapodra with the indicative location of stations en route – view Surat Metro Phase 1 info & route map

Images via follower Mantu Kumar:

After starting out from Kapodra, both machines will be retrieved from Surat Railway Station. Gulermak-Sam’s tunneling plan (drive lengths, estimated timeframe) remains unknown to me, so if anyone is aware then a drop a comment below.

For more updates, check out the Surat section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG