L&T’s 1st Patna Metro TBM Passes Factory Tests

SHARING HELPS OTHERS



China Railway Construction Heavy Industry Co. Ltd. (CRCHI) has completed factory acceptance tests (FAT) on the 1st of 2 new tunnel boring machines for the 30.91 km Patna Metro Phase 1 project’s underground section.

This TBM will be deployed by Larsen & Toubro along with 3 other machines on 14.05 km Line-2’s 8 km Rajendra Nagar – Patna Junction Railway Station section (Package PC-03).

Image via Friends Equipment Heavy Machinery Pvt. Ltd

Delhi Metro Rail Corporation (DMRC) had awarded L&T with package PC-03’s Rs. 1989 crore contract in December 2021 with a 42 month deadline.

PC-03 will connect a ramp near Rajendra Nagar with Patna Junction Railway Station through TBM bored twin tunnels and 6 underground stations at Akashvani (formerly Dak Bungalow), Gandhi Maidan, PMCH, Patna University, Moin Ul Haq Stadium, Rajendra Nagar.

PC-03: Patna Junction – Rajendra Nagar Ramp underground section – view Patna Metro information & route map
L&T’s 1st Patna Metro TBM Passes Factory Tests

Besides 2 CRCHI machines, L&T will deploy 2 THI machines (S71 & S72) previously used for Ahmedabad Metro Phase 1’s tunneling where a final breakthrough was recorded in August 2020.

L&T’s tunneling plan remains unknown to me at this time. If someone reading this is aware, then leave a comment below or shoot me a message via the Contact page.

For more updates, check out the Patna section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG