RVNL Casts Indore Metro Super Corridor Section’s 1st Segment

SHARING HELPS OTHERS



Engineers from Rail Vikas Nigam Ltd. (RVNL) on Monday began pouring concrete to cast segments for Indore Metro Yellow Line‘s 10.927 km MR10 Road – Gandhi Nagar section (Package IN-03).

RVNL was awarded the 33.53 km Indore Metro Phase 1 project’s Rs. 1034 crore contract in September 2021 with a 847 days (2.32 years) deadline. 8.5m wide segments cast at their yard, spread across 15 hectares, near TCS Chauraha will be launched to form the line’s viaduct.

Besides a 575m depot-line, they’ll also be constructing 9 elevated stations at Gandhi Nagar, Super Corridor 6, Super Corridor 5, Super Corridor 4, Super Corridor 3, Super Corridor 2 and Super Corridor 1, Bhawarsala Square and MR 10 Road.

Map of Gandhi Nagar – MR 10 section of Yellow Line via the tender docs – view Indore Metro info & full map

Snaps via RVNL’s Twitter handle:

RVNL Casts Indore Metro Super Corridor Section’s 1st Segment

By back of the hand calculations, I estimate approximately 3000-3200 segments will be cast for this section’s superstructure.

For more updates, check out the Indore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.

– TMRG