Gawar, Krishna & Shiv Win Delhi-Dehradun Expressway’s Work

SHARING HELPS OTHERS



Gawar Construction, Krishna Constructions and Shiv Build India on Friday each won one package of the 210 km Delhi – Saharanpur – Dehradun Expressway after National Highway Authority of India (NHAI) opened financial bids.

This access-controlled expressway is being developed in 4 phases. Its 32 km Phase 1 (Akshardham in Delhi to Eastern Peripheral Expressway) will primarily be a brownfield upgrade, while Phase 2 (EPE Baghpat to Latifpur at Saharanpur Bypass) will be constructed on a greenfield alignment.

Phase 1 – Package 1 (Akshardham to Delhi-UP Border)

Gammon India was the lowest bidder for its original tender. In April, NHAI cancelled that tender and re-invited bids. Technical bids were opened on June 4 to reveal 13 bidders.

Brief Scope: Development of six lane access control greenfield highway of Delhi-Saharanpur-Dehradun EC under BMP from Design Chainage 0.000 (Aksardham NH-9 (old NH-24)) to Design Chainage 14.750 (Delhi-UP Border) in the state of Delhi (Package-1) on EPC mode

  • Length: 14.75 km
  • NHAI’s Estimate: Rs. 1264.33 crore

Financial Bids of Lowest 5 Bidders:

Firm Bid (Rs Crore)
Gawar 1100.00
HG Infra 1114.11
Krishna 1116.00
J Kumar 1135.00
GR Infraprojects 1190.97
Gawar, Krishna & Shiv Win Delhi-Dehradun Expressway’s Work
Delhi – Dehradun Expressway’s route via NHAI’s promo video – view project information

Phase 2 – Package 2 (Lohadda – Karaunda Mahajan)

27 bidders had submitted 49 bids for Package 2 and 3’s original tenders. NHAI cancelled those tenders without offering a reason and shortly re-invited bids. In May, NHAI received 55 bids from 29 bidders for its construction.

Brief Scope: Development of 6 lane access control greenfield highway of Delhi-Saharanpur-Dehradun economic corridor under Bharatmala Pariyojana from Design Chainage 27.000 (Vill-Lohadda) to Design Chainage 56.500 (Vill-Karaunda Mahajan) in UP on EPC Mode (PKG-II)

  • Length: 29.5 km
  • NHAI’s Estimate: Rs. 693.70 crore

Financial Bids of Lowest 5 Bidders:

Firm Bid (Rs Crore)
Krishna 503.00
Raj Shyama 520.13
Gawar 554.96
Galfar 564.00
Ceigall 581.00

Phase 2 – Package 3 (Karaunda Mahajan – Khyawari)

Brief Scope: Development of of 6 lane access control greenfield highway of Delhi-Saharanpur-Dehradun economic corridor under BP from Design Chainage 56.500 (Vill-Karaunda Mahajan) to Design Chainage 82.000 (Vill-Khyawari) in UP on EPC Mode (PKG-III)

  • Length: 25.50 km
  • NHAI’s Estimate: Rs. 633.03 crore

Financial Bids of Lowest 5 Bidders:

Firm Bid (Rs Crore)
Shiv Build India 434.99
Raj Shyama 461.98
Shivalaya 491.00
Krishna Constructions 493.00
SKS Infra 514.96

The lowest bid for each package was ridiculously way below NHAI’s budgeted estimate. NHAI might seek clarification from the lowest bidders for financial bid evaluation, but I believe contracts would eventually be awarded since they’ve all qualified through the technical round.

With this development, winners for all packages of phases 1, 2 and 4 are now known. Design details of this expressway along with a list of all packages and their status can be viewed here.

For more updates, check out the Expressways section or my Home Page!

– TMRG