J Kumar Launches Mumbai Metro Line-2A AC-01’s Final U-Girder
[ad_1]
Last midnight, a crew from J Kumar Infraprojects – CRTG JV launched the final of 680 U-girders for constructing package AC-01 of Mumbai Metro’s 18.6 km Line-2A (Yellow Line) which will connect Dahisar East and DN Nagar.
This major construction milestone using a 16m U-girder weighing 93 T – one of the smallest on the entire line – was achieved between piers P49-P50 next to Dahisar ROB near Upper Dahisar Station.
![](https://themetrorailguy.com/wp-content/uploads/2021/02/MumbaiMetroLine2A5.jpg)
J Kumar-CRTG JV is responsible for constructing both packages AC-01 and AC-02 of Line-2A and completed casting the first batch of U-girders for both this line and the 16.5 km Line-7 at their Bandra yard in January 2017. In July 2017, the team launched the first U-girder in Borivali.
Besides the elevated viaduct, Package AC-01 also includes the construction of 8 stations at Upper Dahisar Station (Anand Nagar), Kandarpada (Rushi Sankul), Mandapeshwar (IC Colony), Eksar, Borivali West (Don Bosco), Pahadi Eksar (Shimpoli, then Shimpawali), Kandivali West (Mahavir Nagar), Dahanukarwadi (Kamraj Nagar).
![](https://themetrorailguy.com/wp-content/uploads/2021/02/MumbaiMetroLine2A7Map.png)
![](https://themetrorailguy.com/wp-content/uploads/2021/02/MumbaiMetroLine2A4.jpg)
![](https://themetrorailguy.com/wp-content/uploads/2021/02/MumbaiMetroLine2A1.jpg)
![](https://themetrorailguy.com/wp-content/uploads/2021/02/MumbaiMetroLine2A6.jpg)
![](https://themetrorailguy.com/wp-content/uploads/2021/02/MumbaiMetroLine2A2.jpg)
The rest of the viaduct’s civil work will be completed using I-girders and steel girders at places like Dahanukarwadi (parallel siding line) and Kandivali West.
MMRDA is publicly chasing a May 2021 deadline, but internally likely has a different target date later in the year. Overall system and station finishing works have a long way to go. A few images of Mandapeshwar (formerly IC Colony) Station – which is in the most-advanced stage of completion – can be viewed here.
I hear the start of installing platform screen doors (PSDs) is another 2 months away. Also, entry-exit locations for 6 stations hasn’t been finalized yet – something which is hard to believe. But looking at the video below, it could very well be true as entry/exit structures are missing throughout.
This video by a local YouTuber was uploaded on February 2 and covers Package AC-01 from end to end between Dahisar East – Dahanukarwadi with the depot-line to Charkop Depot shown at the 11:08 mark. The rest shows Package AC-02 (Dahanukarwadi – DN Nagar), which will open up at a later time in mid-2022 – 23.
For more updates, check out my Home Page!
– TMRG