Madhya Pradesh Metro Rail Corporation Ltd (MPMRCL) today invited tenders for the civil construction work of Indore Metro Yellow Line‘s underground twin tunnels and 7 stations.

8.626 km long underground package IN-05 will connect a ramp east of Indore Railway Station with a ramp west of Indore’s Devi Ahilya Bai Holkar Airport via 7 underground stations located at Indore Railway Station, Rajwada, Chota Ganpati, Bada Ganpati, Ramchandra Nagar, BSF/Kalyani Nagar and Airport.

This is the first and only underground package of the 33.53 km Indore Metro Phase 1 project. On the east-side, it will be connected to Package IN-04 (won by RVNL – URCC JV in December 2023), and on the west-side it will be connected to Package IN-03 (under construction by URCC via a subcontract by RVNL since 2021)

MPMRCL will require the assigned contractor to deploy at least 4 tunnel boring machines (TBMs) for constructing 16 tunnels.

Package: IN-05

Brief Scope: Design & Construction of Twin Tunnel (Up & Down by Shield TBM), Cut & Cover, Cross-passages with/without sump, Ramps, Seven (07) Underground Stations (Indore Railway station, Rajwada, Chota Ganpati, Bada Ganpati, Ramchandra Nagar, BSF/Kalani Nagar and Airport) including Architectural finishing, Plumbing (Water Supply, Sanitary Installation, Drainage facilities and other Plumbing work as directed by the Engineer) works in entire Underground Section from chainage 5+862 to 14+482.347~14+488 for Indore Metro Rail Project

  • Deadline: 1456 days (4 years)
  • Estimated Cost: Rs. 2550 crore
  • Bid Submission Deadline: April 22, 2024 at 4 PM
  • Technical Bid Opening: April 23, 2024 at 4:30 PM
Indicative route of Indore Metro’s underground section – view Indore Metro Phase 1 route map & information

Looking at the scope, I see MPMRCL has combined BSF and Kalani Nagar stations into one, and renamed Maulana Azad Marg Station to Chota Ganpati Station. A station earlier planned at High Court / Hotel Residency, east of the Railway Station, is no longer in the works as it didn’t get featured in IN-04 or IN-05’s scope.

This contract will be financed by the Asian Development Bank (ADB) USD $225 million loan which is currently pending ADB’s board’s approval – see ADB’s project sheet.

This is Yellow Line’s 6th and final civil package to enter the bidding stage – see a list of all Indore Metro packages and their status / contractors over here.

For more updates, check out the Indore section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? See how you can get early-access to updates and support the site over here.