L&T Wins Mumbai’s Nariman Point – Cuffe Parade Bridge’s Contract

[ad_1]


That was awfully quick! Larsen & Toubro on Thursday was declared as the lowest bidder to construct a new bridge between Nariman Point and Cuffe Parade (near Colaba) by the Mumbai Metropolitan Region Development Authority (MMRDA)

As shared earlier this week – this approximately 1.77 km 4 lane bridge will connect Marine Drive, where the 29.80 km Mumbai Coastal Road terminates further up north, with Captain Prakash Pethe Marg near Cuffe Parade Station – the southern terminus of Mumbai Metro’s Aqua Line (Line-3).

MMRDA had invited tenders for the bridge’s civil construction in November 2022 with a Rs. 315 crore estimate and 30 month (2.5 year) completion deadline.

Technical bids were opened on January 4 to reveal 2 bidders and technical bid evaluation was completed within 8 days, something that is unheard of. L&T beat J Kumar Infraprojects by just Rs. 1 crore when financial bids were opened on Thursday afternoon.

Financial Bid Values

Firm Bid (Rs. Crore)
Larsen & Toubro 316
J Kumar Infraprojects 317

Brief Scope: Design and Construction of 4 lanes Bridge connecting Nariman Point to Colaba Cuffe Parade on EPC mode

Bridge’s alignment – via MMRDA’s tender docs

L&T’s bid was 1 crore higher than MMRDA’s estimate, which is negligible, so a contract should be awarded in the coming weeks without a lengthy financial bid evaluation period.

As shared earlier, I’m not a big fan of this bridge. Ideally the entire Bay Bay should be reclaimed which would negate the cost of building the bridge’s sub and super-structure.

For more updates, check out the Expressway section or my Home Page! Sign up for free instant email notifications on new posts over here. Like this post? Get early-access to updates and support the site over here.

– TMRG