STEC Begins Work on Delhi-Meerut RRTS’ TBM Launch Shaft

[ad_1]


Back on June 13, Shanghai Tunnel Engineering Co. Ltd. lowered and concreted the first diaphragm wall (D-Wall) panel for the 82.15 km Delhi – Meerut RRTS project’s southern Tunnel Boring Machine (TBM) launch shaft at Anand Vihar.

STEC is constructing two TBM launch shafts on either side of the upcoming Anand Vihar RRTS Station from where four TBMs will be launched – 2 southwards towards Khichripur to connect with Afcons Infra’s Package 6 and another 2 northwards towards Sahibabad to connect with KEC-CCECC JV’s Package 1.

Route of Package 4 (New Ashok Nagar DN Ramp – Sahibabad UP Ramp) – view Delhi-Meerut RRTS project info & full map

The first D-Wall cage is about 20 meters tall and 5 meters wide. It will help reinforce the soil around it and prevent potential water seepage during excavation.

Photo Copyright: NCRTC

Here’s a snap of Anand Vihar’s southern TBM launch shaft site (20m long x 16m wide):

Photo Copyright: NCRTC

Anand Vihar RRTS Station will be built independent of both TBM launch shafts using the Cut and Cover method below the operational Blue Line (Line-4) and Pink Link (Line-7)’s stations. This will eventually lead to the relocation of some existing structures (entry/exits, DG room, pump room etc) in a phased manner.

For more updates, check out the NCR RRTS section or my Home Page!

– TMRG